Provide a breakdown of the expenditure on the construction of the Millennium Town Park to date
This content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.
1240/5(6814)
WRITTEN QUESTION TO THE MINISTER FOR TRANSPORT AND TECHNICAL SERVICES BY DEPUTY M. TADIER OF ST. BRELADE
ANSWER TO BE TABLED ON TUESDAY 17th APRIL 2012
Question
Further to the response given on 21st February 2012 regarding the breakdown of costs for the Millennium Town Park, would the Minister advise whether there has been any additional expenditure to date?
Answer
There has been no further expenditure over and above the figures stated in the answer to the question on 21st February 2012. The final account for the Park construction has now been settled with the Contractor and all Park and associated works will be completed within the original capital allocation.