Question

Cost of developing the new hospital

Published on: 10 November 2025

Question type: Written

Asked by: Max Andrews

Reference: WQ.408/2025

Answered by: Minister for Treasury and Resources

This content has been automatically generated from the original PDF and some formatting may have been lost, therefore it should not be relied upon to extract citations or propose amendments. Please see the PDF for the official version of the document.

WQ.408/2025

WRITTEN QUESTION TO THE MINISTER FOR TREASURY AND RESOURCES

BY DEPUTY M.B. ANDREWS OF ST HELIER NORTH

QUESTION SUBMITTED ON MONDAY 3rd NOVEMBER 2025 ANSWER TO BE TABLED ON MONDAY 10th NOVEMBER 025

Question

"Will the Minister advise the total cost of developing the new hospital from 2012 to present?"

Answer

A breakdown of the expenditure per annum on initiatives to deliver a new hospital for Jersey, and latterly, New Healthcare Facilities, can be found below. It is important to note that each project has built upon the previous one, reusing information and enabling faster progress toward delivery with every iteration.

 

Initiative

Year

Expenditure (£m)

Notes

Hospital project mandated under P.82/2012

2012

0.0

Progressed to site selection/feasibility before project closure.

2013

0.0

2014

1.4

2015

3.2

2016

4.7

Future Hospital Project

2017

15.0

Progressed to RIBA2 Concept Design before project closure/unsuccessful outline planning application.

Includes £0.9m of site acquisition and associated costs, e.g. stamp duty.

2018

16.6

2019

6.0

Our Hospital Project

2019

0.5

Progressed to RIBA3 Developed Design before project closure and achieved planning consent.

Includes £25m of site acquisition and associated costs, e.g. stamp duty.

Includes £9.6m investment in now operational facilities – Enid Quenault Health and Wellbeing Centre.

2020

10.6

2021

52.2

2022

20.5

New Healthcare facilities Programme

2023

38.4

Overdale project completing RIBA2 Concept Design stage.

Includes £17.6m of site acquisition and associated costs, e.g. stamp duty.

Includes £6.7m investment in now operational facilities – Enid Quenault Health and Wellbeing Centre.

Includes £0.5m demolition at Overdale site – assets under construction.

2024

20.2

Progression of Overdale site design, including Acute Hospital to RIBA3 stage and Planning Application submission

Overdale site demolition complete

Samares at St Ewold refurbishment complete

Includes acquisition of 2 Edward Place

The accounts for 2025 are part year and hence unaudited. Expenditure can be provided once the year is complete and accounts have been audited. The spend to September was £14.9 million.